There are multiple tool event types from the POR Schedule. However, there is a mapping in LSPx to categorise them into three main categories [Install, Demo and Convert in Place (CIP)]. The table below shows all the event types from POR and its category in LSPx. To ensure that DACs can be created for all necessary events, below is a simple rule for determining the type:
- If "Install" is in the word, use the Install form.
- If "Demo" is in the word, use the Demo form.
- If "Conv", "Qual/Qual-Fac" or "Upgrade/Upgrade-Fac" is in the word, use Convert in Place (CIP) form.
Mapping (POR Schedule vs LSPx)
| # | Event Type from POR Schedule | Event Type in LSPx |
|---|---|---|
| 1 | Conv | Convert in Place (CIP) |
| 2 | Conv - Stop Work | Convert in Place (CIP) |
| 3 | Conv-Fac | Convert in Place (CIP) |
| 4 | Conv-Fac - Stop Work | Convert in Place (CIP) |
| 5 | Conv-Fac-Rename | Convert in Place (CIP) |
| 6 | Conv-Rename | Convert in Place (CIP) |
| 7 | Demo | Demo |
| 8 | Demo - Stop Work | Demo |
| 9 | Harvest | N/A |
| 10 | HDQ | N/A |
| 11 | Install | Install |
| 12 | Install - Stop Work | Install |
| 13 | Install-Conv | Convert in Place (CIP) |
| 14 | Install-Conv - Stop Work | Convert in Place (CIP) |
| 15 | Install-Conv-Rename | Convert in Place (CIP) |
| 16 | Install-Conv-Rename-Stop Work | Convert in Place (CIP) |
| 17 | Install-Rename | Install |
| 18 | Install-Rename - Stop work | Install |
| 19 | Qual | Convert in Place (CIP) |
| 20 | Qual - Stop Work | Convert in Place (CIP) |
| 21 | Qual-Fac | Convert in Place (CIP) |
| 22 | Qual-Fac - Stop Work | Convert in Place (CIP) |
| 23 | Qual-Fac-Rename | Convert in Place (CIP) |
| 24 | Stop Work - Conv | Convert in Place (CIP) |
| 25 | Stop Work - Conv-Fac | Convert in Place (CIP) |
| 26 | Stop Work - Demo | Demo |
| 27 | Stop Work - Install | Install |
| 28 | Stop Work - Install-Conv | Convert in Place (CIP) |
| 29 | Stop Work - Install-Conv-Rename | Convert in Place (CIP) |
| 30 | Stop Work - Install-Rename | Install |
| 31 | Stop Work - Qual | Convert in Place (CIP) |
| 32 | Stop Work - Qual-Fac | Convert in Place (CIP) |
| 33 | Stop Work - Upgrade | Convert in Place (CIP) |
| 34 | Upgrade | Convert in Place (CIP) |
| 35 | Upgrade - Stop Work | Convert in Place (CIP) |
| 36 | Upgrade-Fac | Convert in Place (CIP) |
| 37 | Upgrade-Fac - Stop Work | Convert in Place (CIP) |